Tuesday, July 19, 2011

Royesford-Spring City Bridge Stakeholders Meeting [Video]


On Monday, July 11th, Royersford Borough hosted officials from PennDOT Engineering District 6-0 to discuss the status of repair work on the Royersford-Spring City Bridge with the public and business owners in the immediate area. During this briefing, Steve Laws, Assistant Construction Engineer with PennDOT, and Michael Cuddy of TranSystems noted that since a previous stakeholder meeting in February, additional damage found on the deck of the bridge has necessitated a change in PennDOT's repair plans. Construction of an eight-inch reinforced concrete deck on the bridge will require a complete shutdown of structure beginning on July 18th and lasting roughly eight weeks. PennDOT staff discussed the detour plans for the bridge, and addressed the questions/concerns of those in attendance.

0 comments:

 